Excavation of HS2’s twin tunnels towards Euston has passed the halfway point, the railway company announced on Monday, with 2.25 miles dug in each of the planned 4.5-mile bores.
The milestone concerns the underground route from Old Oak Common into central London. It measures progress on excavation, rather than completion of the railway or the start of passenger services.
Work beneath London
HS2 Ltd said its two tunnel boring machines, Karen and Madeleine, began their journeys in January and March 2026. They operate around the clock, advancing at about 16 metres a day.
The tunnel lining will require 48,294 concrete segments manufactured in Hartlepool, according to the company.
What the Euston link is intended to deliver
HS2 says bringing intercity services into its planned Euston station would release capacity on the southern West Coast Main Line, creating opportunities for other services between London and Birmingham.
Passenger operations remain years away. The London Standard reports an expected opening window of 2036–2039 for Old Oak Common–Birmingham services and 2040–2043 for the Euston extension. These are reported forecasts, rather than guaranteed opening dates.