Ardea Resources has begun the federal environmental approvals process for its Goongarrie Hub nickel-cobalt project in Western Australia, lodging a referral under the Environment Protection and Biodiversity Conservation Act.
The proposed development, 70 kilometres north-west of Kalgoorlie-Boulder, is being advanced through a joint venture with Japanese companies Sumitomo Metal Mining and Mitsubishi Corporation. The submission was made to the National Environmental Protection Agency after years of environmental studies.
It covers the proposed mine as well as supporting infrastructure, including borefields and access roads. The referral will trigger a formal Commonwealth assessment to determine whether the project is a “controlled action” because of its potential impact on matters of national environmental significance.
Goongarrie Hub forms centrepiece of nickel project
Goongarrie is the priority development area within Ardea’s broader Kalgoorlie Nickel Project, which has a resource of 854 million tonnes grading 0.71 per cent nickel and 0.045 per cent cobalt.
The resource contains 6.1 million tonnes of nickel and 386,000 tonnes of cobalt. Ardea’s prefeasibility study indicates that its goethite-rich ore could support an operation lasting more than 40 years.
The Goongarrie Hub accounts for most of the resource, with 584 million tonnes grading 0.69 per cent nickel and 0.043 per cent cobalt. It contains four million tonnes of nickel and 250,000 tonnes of cobalt.
The Japanese joint venture partners have contributed $157.3 million towards project studies, including $58.8 million to fund pre-front-end engineering and design work at Goongarrie.
As part of that latest funding arrangement, Sumitomo Metal Mining and Mitsubishi Corporation took on Ardea’s $29.4 million share of the study costs and increased their combined interest in the project’s parent company, Kalgoorlie Nickel Pty Ltd, from 35 per cent to 45 per cent.
Their interest could rise to 60 per cent if a final investment decision is made. The partners will also have final approval over independently peer-reviewed feasibility reports and are entitled to 80 per cent of the project’s mixed sulphide precipitate, up from 75 per cent.
Ardea has retained an option to sell its entire interest from February next year until the investment decision, although the Japanese partners have a higher-priority call option subject to conditions and approvals.
The project has been granted Major Project Status by the Australian Federal Government and has received conditional, non-binding support for potential funding of up to A$1 billion from Export Finance Australia and the US Export-Import Bank.
Ardea also retains full ownership of the Kalpini and Yerilla nickel-cobalt projects near Kalgoorlie, which together have a 270-million-tonne resource containing more than two million tonnes of nickel.
With the EPBC referral now lodged, the Goongarrie Hub has moved into the next stage of its environmental assessment and approvals pathway.