Brisbane City Council has spent almost $2.5 million on consultation and design work for a bikeway promised 13 years ago, yet the final section remains undelivered.
The North Brisbane Bikeway is intended to link the CBD with Redcliffe through 40 kilometres of protected paths. Queensland’s government completed stages one to four, running from Herston to Wooloowin, by early 2021, leaving the council responsible for stage five.
Figures released through a question on notice show the council spent $2.49 million on planning the final stage between 2017 and 2025.
North Brisbane Bikeway route changes
The council abandoned its proposed route along Dickson Street early last year. The plan would have taken the bikeway from Price Street through Keith, Sydney and Jackson streets before joining the Kedron Brook Bikeway.
Instead, it is backing a western alignment that includes Kent Road and intends to seek Queensland Government funding to progress the alternative.
The Kent Road route was originally proposed in 2018 but was rejected after complaints about the loss of on-street parking. Twenty-one months after the council said it would pursue the route again, state funding has not been secured.
A council spokesman said the Dickson Street proposal had prompted concerns about traffic, parking and safety from local residents.
“We listened to those concerns and are backing the alternative Kent Road alignment,” he said.
Hamilton councillor Julia Dixon previously described the project as a “complex matter with varying opinions” and said she supported Kent Road, along with the majority of residents.
However, consultation in 2021 found that 60 per cent of more than 1,000 respondents supported the Dickson Street route. Documents obtained through a Right to Information request also showed that about 70 per cent of members of a community working group backed it in 2024.
The working group included residents, a businessperson, representatives of community organisations, active transport users and visitors who travelled by car or public transport.
A council staff report said opponents of the Dickson Street alignment were concerned about possible effects on businesses and properties, including congestion, the appearance of traffic-calming measures, a proposed right-turn ban at Keith Street and the loss of parking.
Signs opposing the scheme have appeared on several fences along the proposed Dickson Street route, where some residents have mounted fierce opposition.
Labor opposition leader Jared Cassidy criticised the delay, saying: “Each day that active transport investment is stalled, ratepayers pay the price with more dollars spent on designs and more time lost stuck in congestion.”