Forrestania Resources has signed key supply and haulage agreements as it prepares for a first gold pour at its Edna May mine in Western Australia in December.
The company has entered into a long-term agreement with Australian Gold Reagents for sodium cyanide, a chemical required for gold recovery, as the operation moves towards wet commissioning.
It has also appointed Campbell Gold Haulage to load ore and feed the crusher at both the 2.9-million-tonne-a-year Edna May operation and the 3.2-million-tonne-a-year Lake Johnston hub.
Campbell already holds the contract to transport ore by road train to Forrestania’s run-of-mine pads, allowing the company to use the same contractor across its ore-handling operations. Equipment and personnel are now being mobilised to site.
Forrestania prepares for first gold pour
Forrestania said about 60,000 tonnes of ore is currently stockpiled at Edna May, where processing is due to begin shortly. Lake Johnston, which is scheduled to become operational in early 2027, has more than 180,000 tonnes of ore in inventory and a run-of-mine stockpile approaching capacity.
Executive chairman David Geraghty said the latest agreements marked important progress in establishing the company’s operating platform.
“These initiatives represent important milestones in the systematic build-out of Forrestania’s operating platform as we progress toward production at Edna May,” he said.
“With approximately 60,000 tonnes of ore available on the ROM stockpile, and first ore processing at Edna May fast approaching, alongside ore inventories of over 180,000 tonnes and continuing to build at Lake Johnston with the ROM stockpile near full capacity, our focus is on ensuring every element of each operation is in place for a successful transition to production.”
The company has also established an office in Kalgoorlie to act as its Goldfields operations hub. The facility will be shared with its mining contractor, MEGA Resources, and is intended to support Forrestania’s longer-term presence in the region.
Darren Gaby, who has more than 30 years’ experience in operational and project development roles in the Western Australian goldfields, has been appointed general manager mining. He previously led the development of Beacon Minerals’ Jaurdi Gold project from construction through to production.
Forrestania’s hub-and-spoke strategy is based on processing ore from its own deposits at Edna May and Lake Johnston, while also securing additional supplies from local miners through ore-purchase agreements.
The company’s regional expansion was strengthened by its completed takeover of Zenith Minerals. Forrestania now holds a 72.56 per cent controlling interest in Zenith, which added 675,000 inferred ounces of gold to its resource base.
The new contracts and growing stockpiles come as Forrestania moves from dry to wet commissioning at Edna May. The company is targeting its first gold pour in December, with Lake Johnston expected to follow in early 2027.