Locksley Resources has begun a 5,500-metre diamond drilling programme at the Iron Duke copper-gold project in central New South Wales, targeting extensions to high-grade mineralisation that remains open along strike and at depth.
The campaign, the company’s first drilling at Iron Duke, is expected to comprise up to 28 holes. The number completed will depend on results as the work progresses.
Iron Duke currently has an inferred resource of 1.1 million tonnes grading 1.11 per cent copper and 0.61 grams per tonne of gold. Previous drilling has identified high-grade lodes across about 700 metres from near surface, with mineralisation defined to roughly 140 metres below ground.
The steeply dipping lodes range from two to 20 metres in true thickness. Historical results include a 13-metre intersection grading 1.56 per cent copper and 4.48 grams per tonne of gold from 37 metres downhole.
Other earlier drilling returned 24 metres at 1.53 per cent copper and 1.55 grams per tonne of gold from 49 metres, while separate holes recorded 31 metres at 1.13 per cent copper and 0.96 grams per tonne of gold from 34 metres, and 24 metres at 1.07 per cent copper from 32 metres.
Iron Duke drilling to test southern gap
A key target is a 100 to 150-metre gap at the southern end of the system. The area lies along strike from the known high-grade lodes but has received little drilling.
Locksley will also carry out infill drilling through the high-grade core to assess the continuity and geometry of the mineralised shoots. The diamond core is expected to provide structural, bulk-density and metallurgical information that was not available from earlier reverse-circulation drilling.
Ian Stockton, Locksley’s technical director, said the oriented core could help identify the controls on the high-grade shoots and guide further drilling.
“The southern gap sits directly along strike from the high-grade lodes and has seen very little drilling. The oriented core should also show us what controls the high-grade shoots, which is a key to growing Iron Duke and targeting future holes,” he said.
Iron Duke forms part of Locksley’s roughly 1,000-square-kilometre Greater Tottenham land package, held under an option-to-purchase agreement with Sky Metals. The company has identified up to 26,000 metres of potential drilling across the wider project.
That wider programme includes a planned 10,000 metres at Mt Royal–Orange Plains, where Locksley intends to test lightly drilled ground and extensions to known high-grade mineralisation. The Carolina prospect is also in line for future drilling.
Locksley recently reported an increased Greater Tottenham resource of 10 million tonnes grading 1.1 per cent copper and 0.32 grams per tonne of gold, containing 110,000 tonnes of copper and 100,000 ounces of gold.
The project lies within the Cobar Basin and Lachlan Orogen, in a region that includes the Tritton, CSA and Cadia Valley operations. The New South Wales Government has identified copper as one of five priority commodities under its Critical Minerals Strategy, with 21 of 29 projects supported in its latest funding round focused on copper.
Locksley had $13.4 million in cash at the end of September, providing funding for its exploration plans as drilling begins at Iron Duke.