A new construction code introduced after an inquiry into the CFMEU will be applied retrospectively to the 17 venues being delivered for the Brisbane 2032 Olympic and Paralympic Games, Queensland’s Deputy Premier Jarrod Bleijie has announced.
The Games Independent Infrastructure and Coordination Authority (GIICA) requested the change as excavation work at Victoria Park reached its 100th day. Mr Bleijie said he had approved the application on Wednesday.
The productivity code, adopted by the Queensland Government on Tuesday, sets mandatory workplace, safety and industrial relations standards for publicly funded construction projects worth $150 million or more.
Mr Bleijie said the code had initially been intended to apply only to future projects, but a provision allowed ministers to approve its use for current tenders.
“When [Brisbane Stadium] starts being constructed, it would have been under the old EB [enterprise bargaining] arrangements,” he said.
“That’s why we needed the code to apply. However, we did put a provision in the code that said it’s prospective – it’s going forward. But if line agency ministers or agencies wanted the code to apply to current tenders, they have to write to the responsible minister for approval.”
One provision bans unions from requiring contractors to display flags and branding on construction sites. Mr Bleijie alleged that workers could otherwise feel pressured to join the CFMEU.
“And if they get there, they get bullied into joining the CFMEU. That’s not freedom of association,” he said.
The CFMEU has vowed to build the new Brisbane Stadium, where construction was expected to begin by mid-2027, citing its existing enterprise agreement with preferred builders BESIX Watpac and John Holland.
Victoria Park excavation reaches 100 days
At Victoria Park, about 200,000 cubic metres of soil have been moved during the first 100 days of the early works programme for Brisbane Stadium.
GIICA chairman Stephen Conry said about 65 workers had been working six days a week, weather permitting, to prepare the site. The cut-and-fill method was being used to deal with the area’s naturally hilly terrain while limiting truck movements.
Mr Conry said the project validation report for Victoria Park was expected in the first half of 2027, after which construction could begin.
Public consultation for the site’s master plan has concluded, with more than 42,000 people logging on to the Victoria Park precinct website, according to Arup Australia and New Zealand business director Penny Hall.
Ms Hall said feedback had focused on improved connections, more opportunities and open space, alongside concerts and sporting events at the stadium, the National Aquatic Centre and the Royal National Agricultural and Industrial Association grounds.
She described the master plan as a “living document”, adding that changes to the draft released in August had not yet been finalised.
Mr Bleijie also said Exhibition Station would be operating during the Games, despite concerns from the International Olympic Committee about its distance from the planned athletes’ village at the RNA Showgrounds.
Pedestrian access from Fortitude Valley station remains under consideration, with planners examining how to improve the route into the wider precinct.